Power Generation Rebounds as Lagos–Escravos Gas Line Repair Ends Supply Disruption

Nigeria’s electricity generation has recorded a significant boost following the successful repair and restoration of the vandalised Lagos–Escravos–Lagos gas supply infrastructure, the Nigerian Independent System Operator (NISO) has announced. Recall two weeks ago, the Nigerian Petroleum Company (NNPC) Limited confirmed an incident involving an explosion near Tebijor, Okpele, and Ikpopo communities in Gbaramatu Kingdom, Delta […]

Power Generation Rebounds as Lagos–Escravos Gas Line Repair Ends Supply Disruption

Nigeria’s electricity generation has recorded a significant boost following the successful repair and restoration of the vandalised Lagos–Escravos–Lagos gas supply infrastructure, the Nigerian Independent System Operator (NISO) has announced.

Recall two weeks ago, the Nigerian Petroleum Company (NNPC) Limited confirmed an incident involving an explosion near Tebijor, Okpele, and Ikpopo communities in Gbaramatu Kingdom, Delta State causing disruption in power generation. 

Meanwhile, in a statement by NISO Friday, it attributed the improvement to the intervention of the Nigerian Gas Infrastructure Company (NGIC), alongside enhanced gas supply to several critical thermal power plants across the country. The development, according to the operator, marks an important step toward stabilising electricity supply and strengthening the reliability of the national grid.

“The Nigerian Independent System Operator (NISO) is pleased to announce a notable improvement in power generation following repair and restoration of the vandalized Lagos-Escravos-Lagos gas supply infrastructure by the Nigerian Gas Infrastructure Company (NGIC) and the enhancement of gas supply to several key thermal power plants across the country,” the statement said.

NISO explained that power restoration is being carried out cautiously to avoid putting undue pressure on the system. “Currently, gradual power offtake is being carried out by the affected plants to ensure a smooth recovery and maintain the stability of both the gas supply network and the national electricity grid,” it noted, adding that the approach is designed to prevent system stress while meeting the electricity needs of “industries, businesses, and households.”

The system operator further disclosed that additional thermal power plants are on standby, pending confirmation of gas supply from their suppliers. According to NISO, these confirmations are expected “between now and Saturday, 27th December 2025,” after which the plants will be integrated into the grid to boost generation capacity and minimise the risk of outages.

Reaffirming its commitment to sustained improvements, NISO said it is working closely with power generation companies, gas suppliers, and regulatory authorities to track developments and resolve operational issues promptly. “The organization remains committed to sustaining these improvements and ensuring a reliable, efficient, and resilient power system that supports Nigeria’s socio-economic development,” the statement added.

NISO also appealed to electricity consumers nationwide to use power responsibly during the recovery period. “NISO urges all consumers to continue practicing energy conservation where possible, as the coordinated efforts to stabilize power supply progress,” it said.

<